Punjab Submits Revised Kiratpur Sahib-Nangal NH-503 Four-Laning Plan to NHAI as Rs 2,700 Crore Cost Raises Concerns

The Punjab Government has submitted a revised design for the proposed four-laning of the Kiratpur Sahib-Nangal stretch of National Highway 503 to the National Highways Authority of India (NHAI), as the project continues to face delays over costs and land acquisition.

The revised proposal covers an approximately 30-kilometre section of the highway and includes changes intended to address concerns raised during the earlier planning process.

Ropar Deputy Commissioner Komal Mittal confirmed on Thursday, November 19, 2026, that the updated three-dimensional design had been forwarded to NHAI for approval.

However, certain areas around Nangal have been excluded from the first phase because revenue records relating to land in four villages are unavailable.

The highway project has faced difficulties after its detailed project report estimated the cost of four-laning at approximately Rs 2,700 crore.

This was substantially higher than the Rs 1,200 crore sanctioned by the Union Government, which includes approximately Rs 400 crore allocated for land acquisition.

Following the increase in estimated expenditure, the Union Ministry asked Punjab authorities to revise the proposal and bring the project cost within the sanctioned financial limit.

Punjab Education and Local Bodies Minister Harjot Singh Bains, who has been pursuing the development with central authorities, attributed the higher estimates to errors made by the consultants preparing the project.

Bains said he was continuing discussions with the Union Ministry and expressed hope that land acquisition work could begin after the necessary issues were resolved.

Land records have been another major obstacle. Earlier, discrepancies involving 14 villages had affected progress on acquiring the land required for the road expansion.

According to officials, most of those issues have now been addressed, with disputed land parcels transferred into the name of the National Highway authorities.

However, missing revenue records in four villages near Nangal continue to prevent those sections from being included in the initial phase.

The project has also been affected by broader land acquisition difficulties associated with highway construction in Punjab.

According to sources cited in the report, the Union Ministry has adopted a cautious approach to new highway projects and has sought substantial completion of land acquisition before tenders are issued.

Resistance from some farmers over the acquisition of agricultural land has further complicated infrastructure development in different parts of the state.

The proposed widening of the Kiratpur Sahib-Nangal highway is intended to improve road capacity and connectivity in the region, although its eventual construction schedule remains uncertain.

The submission of the revised design represents progress in the planning process, but NHAI approval, land acquisition and completion of the necessary administrative procedures are still required before the project can move forward.